Project name: Renovation of the Teutonia Building to house the Orient Institute Istanbul

Employer: Max Weber Stiftung

Location: Istanbul, Beyoglu

Project Start Date: 2017-2023

Construction area: 2474 m²

Project scope:
Phase One: Interior project design – 2017
Second Phase: Supervision services 2019-2023
Third Phase: Implementation of the interior design project 2023

Following the conclusion of the architectural project by Çırakoğlu Architecture and the German ARGE Group, the construction tender was issued by the employer. Construction works commenced in May 2019 and were completed in 2023.

The concept and implementation projects were conducted by the Mor Architecture team under the direction of Yasemin Saygıner. 